# How do I choose between options with a VKT?

Checked 2026-11-15 against GilbApp d5296208bbffa2ab70076e6194f5537c4be1ddf7.

Press "＋ New" in "Plan", choose "Value Kick-out Table", type a tag, press "Create", "+ Add Ends &amp; Means", search and select Values and options.

## Before you start

You need to be [signed in to GilbApp](http://support.gilb.com/help/how-do-i-sign-in-to-gilbapp) on a computer, with a vault you can write to, such as [your own vault](http://support.gilb.com/help/how-do-i-create-my-first-vault). The options must exist as [Solutions](http://support.gilb.com/help/how-do-i-write-a-solution-in-my-plan), and [the Values they touch](http://support.gilb.com/help/how-do-i-write-a-value-in-my-plan) with "Status", "Tolerable" and "Goal" numbers. For the ratios, you also need a [Development Resource](http://support.gilb.com/help/how-do-i-write-a-resource-and-set-the-projects-currency) with "Status" and "Budget". The pictures show a made-up person on a test site; your screen shows your own name and address.

## Steps

1. Press "Main menu" at the top left and choose "Plan".

   Press "Main menu", next to your profile picture at the top left, and under "YOUR SECTIONS" choose "Plan". The button shows the name of the section you are in, such as "Vaults".

   A panel headed "GO TO" opens; "Plan" reads "Your Kai-Zen plan: Functions, Values, Development Resources and Solutions." You can also press the "Plan" button on the card of a vault \(the place where a person or a group keeps their records\) in "Vaults". The "Plan" screen lists your plan records and has the views "Grid", "Graph", "Both" and "Card".

   ![GilbApp with the "GO TO" panel open, and "Plan" under "YOUR SECTIONS" outlined in orange.](http://support.gilb.com/help/media/5060991da780ba07.png)
   What you see: The "GO TO" panel is open over the screen. Look in the left column under "YOUR SECTIONS": the outlined row is "Plan", with the line "Your Kai-Zen plan: Functions, Values, Development Resources and Solutions." Press it to open the Plan screen.
2. Press "＋ New".

   Press "＋ New" at the top right of the "Plan" screen. With no record selected, the type dialog opens at once.

   If a record is selected, "New" first offers five choices: "Create a record and link it to" the selected record, "Link" the selected record "to a record that already exists", "Create a record on its own", "Create a virtual folder" and "Upload a file". Choose "Create a record on its own". A new Value Kick-out Table needs nothing else; the others make a record joined to the selected one, link two records that already exist, make a virtual folder or upload a file. In "Plan", the "GO TO" panel also has "New plan record", which does the same.

   ![The "Plan" screen listing a few plan records with none selected, with the "＋ New" button at the top right outlined in orange.](http://support.gilb.com/help/media/9c69e3e39e838a38.png)
   What you see: The "Plan" screen lists your Values, the Development Resource and the Solutions, with none selected; "VAULT" names your vault. Press the outlined "+ New" button at the top right.
3. Under "TYPE", choose "Value Kick-out Table".

   In the list under "TYPE", choose "Value Kick-out Table", near the end. A Value Kick-out Table \(VKT\) is a table that picks one of several options.

   The dialog opens headed "New function" with "Function" chosen; after you choose "Value Kick-out Table" it is headed "New value kick-out table". The chosen type then shows under "TYPE" with a "DEFINITION" read from GilbVeda, the shared list of terms; it can be long, and you need not read it. "×" beside the type brings the list back. "Value Decision Table", just above, ranks a set of options to use together; [the answer on comparing Solutions in a VDT](http://support.gilb.com/help/how-do-i-compare-solutions-in-a-vdt) covers it. A search box above the "TYPE" list narrows it as you type, and "Close" at the top of the dialog closes it like "Cancel"; you need neither. "↗" at the end of a row shows what GilbVeda says about that type; you do not need it. "Cancel" closes the dialog without making anything. Where it shows "Back" instead, "Back" returns you to the five choices.

   ![The new-record dialog headed "New function" with the list under "TYPE", with the "Value Kick-out Table" option outlined in orange.](http://support.gilb.com/help/media/a9a18237a3b2a7be.png)
   What you see: A window headed "New function" is open. Under "TYPE" the list shows the plan types; it is scrolled so "Value Kick-out Table" shows. Press the outlined option "Value Kick-out Table".
4. Type a tag in "TAG" and press "Create".

   Type a tag in "TAG", keep "Product: Product Values × Solutions" under "LEVEL", check "CREATE IN", and press "Create". A tag is the short name of a plan record: an area, a dot and a keyword, such as Save.Pick.

   "LEVEL" opens on "Product": Product Values down, options across; it cannot be changed after "Create". The box shows "Area.Keyword, e.g. Product.KickOut" until you type. With the tag empty the screen says "Give it a Tag first: a Plan card is named by its Tag." Under "CREATE IN", choose the vault where it will live; vaults you can only read say "read only, you cannot create there". If the tag is already used in that vault, the screen says "is already used in this vault. Pick another." If the vault is not the one you are viewing, the dialog stays open and says the record was made there, "not in the vault you are viewing. It is not drawn here.", with an "Open it" button. "More value kick-out table details" holds an optional "Title" and "Description".

   ![The dialog headed "New value kick-out table" with a made-up tag under "TAG" and "Product: Product Values × Solutions" under "LEVEL", and the "Create" button at the bottom right outlined in orange.](http://support.gilb.com/help/media/a2d3f1b84502ea66.png)
   What you see: The window is now headed "New value kick-out table". "TAG" holds a made-up tag, and "LEVEL" shows "Product: Product Values × Solutions". Press the outlined "Create" button at the bottom right.
5. Press "+ Add Ends &amp; Means".

   At the top of the new table, press "+ Add Ends &amp; Means": the ends are the Values and Development Resources the choice touches, and the means are the options. The button then reads "Done".

   After "Create", the table opens in the middle of the screen; if it shows in the right pane instead, press "Open the table" there. Its top line shows "Value Kick-out Table:" and its tag, "+ Add Ends &amp; Means", "Level: Product \(Product Values × Solutions\)" and "Details", which shows the table's own details in the right pane. Pressing the tag lists every Value Decision, Kick-out and Tracking Table in the vault; choose one to open it. Until you choose rows and columns, the table says "This table has no Values or Solutions yet. Press Edit to choose them."; the button it means is "+ Add Ends &amp; Means". Only a person who may write the table sees that button.

   ![A new Value Kick-out Table in the middle of the screen, still empty, with the "+ Add Ends &amp; Means" button beside its heading outlined in orange.](http://support.gilb.com/help/media/0a546a20bc26d890.png)
   What you see: The new table opens in the middle of the screen, headed "Value Kick-out Table:" and its tag. It says "This table has no Values or Solutions yet." Press the outlined "+ Add Ends &amp; Means" right of the heading.
6. Under "Rows: Product Values and Development Resources", search and select the Values and Resources.

   Type part of a tag in the box that shows "Find a Value or Development Resource by tag" and select it, once for each Value the choice touches and each Development Resource the options use. A Value is a perceived benefit, measured as a number; a Development Resource is what the work uses up, such as money or time.

   Each one you choose becomes a row and shows above the box with a "×", which takes it out of the table, not out of the vault. Only Values at the table's level, "Product", are offered \(a Value that shows "Product" because no level was chosen counts there too\), and Development Resources of any level. "+ New" beside the box makes a new card instead: it opens a box that shows "Tag, e.g. Usability.Learn", holding what you typed, with "New Value \(Product\)", "New Development Resource" and "Cancel". Without a Development Resource, the ratios end in "no cost yet".

   ![The table's row and column pickers, with three Values and Resources chosen as rows, and the find box under "Rows: Product Values and Development Resources" outlined in orange.](http://support.gilb.com/help/media/2599adc21e5d5443.png)
   What you see: The row picker is open under "Rows: Product Values and Development Resources", with three chips chosen: Usability.Save, Offline.Save and Cost.Monthly. The outlined box "Find a Value or Development Resource by tag" is empty again; type a tag in it and choose the match to add a row.
7. Under "Columns: Solutions", search and select each option, and press "Done".

   Type part of an option's tag in the box that shows "Find a Solution or option by tag" and select it, once for each option; then press "Done". Each option is a Solution, how a Function \(what a system does\) gets done; write a missing one first, as the answer on writing a Solution in your plan shows.

   Each option becomes a column, even before it has an impact; Kai-Zen compares 2 to 10 options. A "Solution Constraint" \(a Solution a named person requires\) is offered too. "+ New" beside the box makes a new Solution from the tag typed in it, and "×" beside a chosen one takes it out of the table only. The table then shows, for each row, its "Status" \(where it stands now\), "Tolerable" \(the survival limit\) and "Goal" \(the number you plan to reach; "Budget" for a Resource\), and a column per option, with the rows of sums and "Winners" on top. "Order", "Size", "Full screen" and "Refresh" above it change only how it is shown, or read it again; you need none of them.

   ![The table's pickers with three rows and two options chosen, and the "Done" button beside the table's heading outlined in orange.](http://support.gilb.com/help/media/130ce9e1dbe267c1.png)
   What you see: Under "Columns: Solutions" the chips Save.LocalFirst and Save.ServerFirst are chosen, and the table is drawn below. Press the outlined "Done" right of the heading "Value Kick-out Table:" to close the pickers.
8. Press the cell where an option meets a Value.

   Press the cell in an option's column and a Value's row. The right pane opens under "IMPACTS", headed by the option's tag, "→" and the Value's tag.

   An empty cell shows "+" when you point at it. An impact, the effect an option has on a Value or a Development Resource, fills its cell by itself once written on the Solution's card: the change, then "Tol" and "Goal" with a % \(how much of the way from "Status" to "Tolerable", and to "Goal", that option alone goes; a Resource's cell shows "Tol" and "Bud", toward its "Tolerable" and "Budget"\), "EL" \(the Experience Level\) with its number, and the evidence. With no "Tolerable" or "Goal" on the Value, the cell says "No % yet". The line above the table says "Numbers in this colour open and can be edited. The rest are calculated or read-only.", or "You can open every number to read it. None can be edited here."

   ![The Value Kick-out Table with two option columns and three rows, all cells empty, with the cell where Save.LocalFirst meets Offline.Save outlined in orange.](http://support.gilb.com/help/media/9c3257c1289ea5ce.png)
   What you see: The pickers are closed and the table shows the columns Save.LocalFirst and Save.ServerFirst. The outlined cell is where Save.LocalFirst meets Offline.Save; it is empty and shows a small "+". Press it.
9. Press "+ Add an impact", type the change and press Enter.

   In the right pane, press "+ Add an impact", type the change the option brings, such as -2.8 or +100, and press Enter \(for a Resource, the amount it uses\). You type the change, not the end number: -2.8 on a "Status" of 3 makes 0.2.

   The impact then shows in the cell, and on the Solution's card under "Impacts". If you leave the box with nothing typed, no impact is made; text that is not a number gets "Enter a decimal number." The Value needs one number under "Status" first. Under "HOW SURE", the "Experience Level" shows "1 — An idea or a theory only." until you choose another; [the answer on comparing Solutions in a VDT](http://support.gilb.com/help/how-do-i-compare-solutions-in-a-vdt) shows it, the "±" range and the "EVIDENCE". Repeat steps 8 and 9 for each cell; in the sums, an empty cell adds nothing.

   ![The table with the right pane open under "IMPACTS" for Save.LocalFirst and Offline.Save, with the "+ Add an impact" button outlined in orange.](http://support.gilb.com/help/media/09f073497cf7c4e0.png)
   What you see: The right pane shows "IMPACTS" and the title "Save.LocalFirst → Offline.Save". Press the outlined "+ Add an impact" button under the title, type the change and press Enter.
10. Leave out each option that leaves a Value below "Tolerable".

    In each Value's row, read each option's "Tol" %. By the Kai-Zen method, an option that leaves a Value below "Tolerable", or breaks a constraint, something that must be done because a named person requires it, is out, and the best ratio of Value to cost among the rest wins.

    "Tol" is how much of the way from "Status" to "Tolerable" the option alone goes: at 100 % it reaches "Tolerable", below that it falls short, and a minus % moves the Value away. "past Tolerable" in a cell means the Value was already past it and stays there. An option with no impact on a Value below "Tolerable" leaves it there. Example: an option that does not move Offline.Save from its "Status" of 0 leaves it below a "Tolerable" of 95, so it is out. "Winners Goal", "Winners Tolerable" and "Winners Goal Experience Level" rank the options by three ratios of Value to cost; 1, in bold, is the best. GilbApp does not check constraints: hold each option against your Constraints yourself.

## Deeper

Also asked:

How do I choose when I am unsure what to do? Score your options in a "Value Kick-out Table": an option that leaves a Value below its "Tolerable" is out, and the best ratio of Value to cost among the rest wins. Kai-Zen does this itself for a choice it would otherwise ask you about.

What are a "Value Decision Table", a "Value Kick-out Table" and a "Value Tracking Table"? A Value Decision Table ranks options by how much they move the Values for their cost. A Value Kick-out Table picks exactly one of several options. A Value Tracking Table follows your Values across your steps: the Estimate before each step, the Actual after.

GilbApp ranks every option and kicks none out: the rule in step 10 is the Kai-Zen method's. When the three "Winners" rows put different options first, the method's rule says only that the best ratio wins, not which of the three decides. GilbApp carries nothing out and writes no log line: you carry out the winner yourself. The table's "Description" is a place to note the choice: in the dialog its box shows "The alternatives, and the one that stays."

In GilbApp today a Value Kick-out Table is drawn like a Value Decision Table: it also shows "Combined Tolerable", "Combined Goal", "Combined Worst Case" and "Best set", which add the options together. In the Kai-Zen method the options of a VKT are alternatives, not a set, so these do not apply to it. [The answer on comparing Solutions in a VDT](http://support.gilb.com/help/how-do-i-compare-solutions-in-a-vdt) explains every row and column.

Kai-Zen uses a VKT, when it can, for a choice it would otherwise ask you about, such as a method, a tool, an estimate, or a "Status", "Tolerable" or "Goal": it decides it itself and tells you in one line; you may change it later. It takes the Values and Development Resources of the work that the choice affects, lists 2 to 10 options, and fills a table like a Value Decision Table, without the Combined columns: it picks exactly one.

An option that leaves a Value below its "Tolerable" \(the survival limit\), or breaks a constraint, is out; the best ratio of Value to cost among the rest wins. Kai-Zen makes its own estimates, costs included, if none are given, sets the Experience Level to match, and never skips the table. It keeps every number a person set, as [the answer on what happens if the AI estimates a level you set](http://support.gilb.com/help/what-if-the-ai-estimates-a-level-i-set) explains.

It does not ask you and does not offer the losing options again: it carries out the winner and writes one line in the work's log: the choice, the winner and its ratio; in the chat, that line ends its answer. When a fact or choice that only you have turns up after its one round of questions at the start, Kai-Zen chooses it the same way, writes it on the card as an assumption, with an AI agent as its source, and lists it for your approval at the end. Some acts it always stops and asks you about first, such as a release, ending a record, or spending over a "Budget".

A Value Kick-out Table compares one pair of levels, as a Value Decision Table does. "LEVEL" also offers "Business: Business Values × Stakeholder Values" and "Stakeholder: Stakeholder Values × Product Values": their options are the Values of the level below, and the heading over the second box says so. At those levels, with no Development Resource row, the table has no ratios and no best set: a Value draws no development cost. [The answer on the levels of a plan](http://support.gilb.com/help/what-are-the-levels-of-a-plan) explains the levels.

This answer is written for a computer screen.

Source: GilbApp af0f04ee838a4d55887d2ff1f72edd49a4ff7ca0 \(https://gilb.com/app/version.json read 2026-11-09, buildTime 2026-11-09.522Z, dirty false\); code read at af0f04ee \(no checkout\). Same screens, with the VKT's own words: planKinds.ts:17 \("Value Kick-out Table"\); recordTypes.ts:459-472 \("New value kick-out table", "Area.Keyword, e.g. Product.KickOut", "What the table chooses between.", "The alternatives, and the one that stays."\), :270-291 \(LEVEL\); tableMembership.ts:44-48 \(heading "Value Kick-out Table"\); TableCard.tsx:627-700 \(same card for all three kinds; only a Value Tracking Table differs, :345-347 \`isVtt\`\); PlanTable.tsx:651-657, :833-839, :871-905, :1926-1927 \(Combined columns, Winners, Best set left out only for a Value Tracking Table or a costless pair\); valuePercent.ts:54-101 \(% Tolerable: a gain counts only up to Tolerable, so 100 % reaches it; past Tolerable scored on its side, 0 while it stays, minus when it falls\); planTable.ts:331-347 \("Tol" and "Goal" line, "past Tolerable" note\); no kick-out, constraint or log logic in planTable.ts, bestSet.ts, TableCard.tsx. Standards \(2026-11-09\): Kai-Zen.VKT \(Entry.Choice, Ends, Options 2 to 10, Table without the Combined columns, Execute, Log\), Kai-Zen.VKTRules \(Alternatives, TolerableFirst, NoHuman, Estimate, HumanSet, Constraints\), Kai-Zen.AskRules.Decide \(method, tools, estimates, Status, Tolerable and Goal; tell in one line; may change later\), .Assume \(Assumption, source AiAgent, end approval\), .One, Kai-Zen.ConstraintRules.Options, Agent.VDT.Choices. GilbVeda public read: t:ValueKickOutTable \("CHOOSES EXACTLY ONE OF SEVERAL ALTERNATIVE OPTIONS ... no Combined columns ... An option that leaves a Value below Tolerable, or breaks a constraint, is kicked out; the best Value-for-cost ratio among the rest wins, is carried out, and is logged in one line"\). Resource row and cell words planTable.ts:228-240 \("Budget &lt;n\>" under the one "Goal" heading, PlanTable.tsx:832; the row was already said by the shared "Budget" for a Resource\), :296-300 \("Tol &lt;n\>% · Bud &lt;n\>%"\), :333 \("Tol &lt;n\>% · Goal &lt;n\>%"\); valuePercent.ts:163-177. Live answers: How do I compare Solutions in a VDT?; How do I pick the next step? \(Value Tracking Table\).